Most environmental professionals delvier a Phase I Environmental Site Assessment in two to six weeks from the signed engagement to the final report. The site visit takes a few hours. Most of the time goes to gathering records, and the pace is usually set by how fast government agencies respond. TXCREI typically delivers Phase I reports in 5 to 10 business days.

What happens, step by step

Several of these steps run at the same time, which is how a Phase I can be done in under two weeks.

  1. Engagement (day 1). You sign the agreement, confirm the property, and receive the user questionnaire.
  2. Records ordered (days 1–2). The consultant orders the government database report, historical aerial photos, fire insurance maps, and city directories. Records requests go out to TCEQ, the city, and the fire departments and other agencies.
  3. Site visit (usually days 2–5). The environmental professional walks the property and looks at adjoining properties. Interviews with the owner, manager, or occupants often happen the same day, if they are available.
  4. Records review (days 3–8). The consultant reviews the history and the agency responses as they come in.
  5. Report (days 6–10). Findings are written up, the environmental professional signs, and the report is delivered.

What causes delays

Slow records requests. Under the Texas Public Information Act, an agency that can’t produce records within 10 business days must tell you in writing when it will. If the agency asks the Attorney General for a ruling, it can take much longer. We find most cities take a month or more to get data to us. 

Site access. Locked suites, unavailable tenants, or an owner who won’t schedule the walk-through hold up the visit.

Missing user questionnaire. The buyer’s questionnaire is part of the standard. A report can’t be finished without it.

Complex history. Industrial sites, former gas stations, and multi-tenant centers with a dry cleaner take more research.

Add-ons. Asbestos, lead paint, or vapor encroachment screening can extend the schedule if requested as part of the report.

How to keep your Phase I on schedule

  • Order it as soon as the contract is signed. Don’t wait for financing to be settled.
  • Return the user questionnaire right away.
  • Send any prior environmental reports, site plans, and a list of past tenants before the onsite visit.
  • Give the consultant an owner or manager contact and arrange access to all areas.
  • If you also need a Property Condition Assessment, order both together. One site visit can cover both, and PCRs are usually delivered faster.

How long the report stays valid

Key parts of the Phase I (interviews, lien search, government records review, site visit, and the environmental professional’s declaration) must be completed within 180 days before you acquire the property. A report between 180 days and one year old can be updated by redoing those parts. After one year, you need a new report. If your closing date might slip, keep an eye on that 180-day window.

Frequently asked questions

Can a Phase I be rushed? Sometimes. The site visit and report writing can be sped up, but agency records arrive on the agency’s schedule. Ask your consultant early if your deadline is tight.

What happens if a REC is found? The consultant may recommend a Phase II, which involves soil or groundwater testing and adds several weeks. See Phase I vs. Phase II.

Does a Phase I include asbestos or mold testing? No. Those are non-scope items under ASTM E1527-21 and can be added separately. Adding them may extend the schedule.

Who can perform a Phase I? It must be done by, or under the supervision of, an environmental professional as defined in the federal AAI rule (40 CFR Part 312). That generally means a P.E. or P.G. license, a state environmental license or certification, or a science or engineering degree, each combined with several years of relevant experience, or ten years of full-time relevant experience.

How much does a Phase I cost? See How Much Does a Phase I ESA Cost in Texas?

 

Tony Pynes

About the author

Tony Pynes is a Certified Master Inspector specializing in commercial, industrial, and historical properties. TXCREI is a veteran-owned firm. Tony flies his Beechcraft Bonanza to sites anywhere in Texas at no travel charge. Phase I reports are delivered in 5–10 days and PCRs in 1–3 days. Read What Is a Phase I ESA?, learn more about our Phase I ESA service, or request a quote.

Call Now Button